Xcelsius – Enable Component Properties When Showing Disabled

Question:  Have you noticed that sometimes when using a progress bar you are unable to change the settings on the “Progress Movement?”  That it will appear grayed out?

Answer: This is due to selecting a cell for the Data in the “General” tab where no values are currently populated.

To fix this issue, put dummy data into the cells of your selection and reselect the cell or range of cells.  Once the progress bar is able to see data in the cells, the properties for the “Progress Movement” will become fully visible so you can make the required changes.

 